Contract Capacity Sample Clauses
Contract Capacity. The electric power producing capability of the Generating Facility which is committed to Edison.
Contract Capacity. The generation capability designated for the Project shall be the contract capacity in MW designated in the Cover Sheet, net of all auxiliary loads, station electrical uses, and Electrical Losses (the “Contract Capacity”). Throughout the Delivery Term, Seller shall sell and deliver all Product produced by the Project solely to Buyer. In no event shall Buyer be obligated to receive, in any Settlement Interval, any Surplus Delivered Energy. Seller shall not receive payment for any Surplus Delivered Energy. To the extent Seller delivers Surplus Delivered Energy to the Delivery Point in a Settlement Interval in which the Real-Time Price for the applicable PNode is negative, Seller shall pay Buyer an amount equal to the Surplus Delivered Energy (in MWh) during such Settlement Interval, multiplied by the absolute value of the Real-Time Price per MWh for such Settlement Interval.]
Contract Capacity. The “Contract Capacity” is the full generation capacity of the Project net of all Station Service which shall be [___MWac] and [___MWdc]. Throughout the Delivery Term, Seller shall sell and Schedule all Product associated with the Contract Capacity of the Project [For FCDS bids and for Projects located outside of the CAISO insert: ,including Capacity Attributes,] solely to Buyer, except in the case of an Event of Default of Buyer or an unexcused failure by Buyer to Schedule, receive, and pay for Product under Section 3.1(h)(ii).
Contract Capacity. During the Delivery Term, Seller grants, pledges, assigns and otherwise commits and shall deliver to Buyer for its exclusive use, Distribution Services pursuant to the terms and conditions contained herein at the “Contract Capacity,” which shall be the lower of (a) the Initial Contract Capacity or (b) the quantity of Distribution Services specified in Section 5.1(b) as a result of a Performance Test. The “Initial Contract Capacity” is the amount specified in Appendix II.
Contract Capacity. (a) The Contract Capacity shall be specified in the Purchase Power Agreement and shall not exceed the capacity specified in the Seller’s Interconnection Agreement. This term shall mean the maximum continuous electrical output capability expressed on an alternating current basis of the generator(s) at any time, at a power factor of approximately unity, without consuming VARs supplied by Company, as measured at the Point of Delivery and shall be the maximum kWAC delivered to the Company during any billing period. The Seller shall not exceed the existing Contract Capacity unless and until the increase has been agreed to in an amendment executed by Company and Seller and Seller’s facilities have been upgraded to accept the actual or requested increase as may be required by Company in its commercially reasonable discretion.
(b) The Seller shall not change the Contract Capacity, or contracted estimated annual energy production without adequate notice to the Company, and without receiving the Company's prior written consent, and if such unauthorized increase causes loss of or damage to the Company’s facilities, the cost of making good such loss or repairing such damage shall be paid by the Seller.
(c) The Company may require that a new Contract Capacity be determined when it reasonably appears that the capacity of the Seller's generating facility or annual energy production will deviate from contracted or established levels for any reason, including, but not limited to, a change in water flow, steam supply, or fuel supply.
(d) The Seller may apply to the Company to increase the Contract Capacity during the Contract Period and, upon approval by Company, and an amendment to implement the change has been executed by the Company and the Seller, future Monthly delivered capacities shall not exceed the revised Contract Capacity. If such increase in Contract Capacity results in additional costs associated with redesign or a resizing of Company’s facilities, such additional costs to the Seller shall be determined in accordance with the Interconnection Agreement.
(e) Any Material Alteration to the Facility, including without limitation, an increase in the Existing Capacity, a decrease in the Existing Capacity by more than five (5) percent or the addition of energy storage capability shall require the prior written consent of the Company, which may be withheld in the Company’s sole discretion, and shall not be effective until memorialized in an amendment executed by the Co...
Contract Capacity. The capacity of the Project shall be the Contract Capacity listed in the Cover Sheet (the “Contract Capacity”). Throughout the Delivery Term, Seller shall sell all Product produced by the Project solely to Buyer. In no event shall Buyer be obligated to receive or pay for, in any hour, any Product, as measured by Delivered Energy, that exceeds the Contract Capacity.]
Contract Capacity. 20 MW. The Contract Capacity may be reduced as set forth in Section 3.06(g).
Contract Capacity. The generation capability designated for the Project shall be [___________] MW (AC) net of all auxiliary loads, station electrical uses, and Electrical Losses (the “Contract Capacity”). Throughout the Delivery Term, Seller shall sell and Schedule all Product produced by the Project (net of station use) solely to Buyer and Buyer shall purchase all Product produced by the Project; provided, however, that in no event shall Buyer be obligated to receive or pay for, in any hour, any Delivered Energy that exceeds one hundred and ten percent (110%) of Contract Capacity.
Contract Capacity. Contract capacity is the following amounts for and during the following periods:
Contract Capacity. The generation capability designated for the Project shall be the contract capacity in MW designated in the Cover Sheet, (the “Contract Capacity”). Throughout the Delivery Term, Seller shall sell and deliver all Product produced by the Project solely to Buyer. In no event shall Buyer be obligated to receive, in any Settlement Interval, any Surplus Delivered Energy. Seller shall not receive payment for any Surplus Delivered Energy. To the extent Seller delivers Surplus Delivered Energy to the Delivery Point in a Settlement Interval in which the Real-Time Price for the applicable PNode is negative, Seller shall pay Buyer an amount equal to the Surplus Delivered Energy (in MWh) during such Settlement Interval, multiplied by the absolute value of the Real-Time Price per MWh for such Settlement Interval.