Progress Records Clause Examples for Any Agreement

The Progress Records clause requires one party, typically a contractor or service provider, to maintain and provide regular documentation of the work completed or milestones achieved during a project. This may involve submitting written reports, logs, or other forms of evidence that detail the status and advancement of the project at specified intervals. By mandating the creation and sharing of these records, the clause ensures transparency, enables effective monitoring of progress, and helps both parties identify and address potential delays or issues early in the project lifecycle.
Progress Records. CM will maintain records of the progress of construction of Project construction, including written progress reports and photographs reflecting the status of construction and percentage completion of the Assigned Project. CM will maintain daily records during construction of the Assigned Project showing weather conditions, personnel of the Contractor and its Subcontractors at the Site, work accomplished, problems encountered and other matters materially affecting the Assigned Project, completion of the Assigned Project or Construction Costs to complete construction of the Assigned Project.
Progress Records. Construction Manager will keep detailed records of the progress of the Project during all stages of construction in accordance with the Specifications and this Agreement. Construction Manager will also maintain a daily log of all events occurring on the Project Site or connected with the progress of the Project, a log pertaining to all Requests for Information (RFI) submittals and a log for Contingency Use Request (CUR) submittals. Copies of the progress records and logs will be submitted monthly to Owner.
Progress Records. The CM shall keep accurate and detailed written records of Project progress during all stages of construction. The CM shall maintain a detailed daily diary of all events, which occur at the jobsite or elsewhere, and which affect, or may be expected to affect, Project progress. The diary shall record weather data, including minimum and maximum temperatures, precipitation type and amount, sky conditions, and wind velocities. The diary shall also record all visitors, number of on-site workers for each contract and include a detailed list of all material deliveries to the site. The diary shall be available to the Owner at all times and shall be turned over to the Owner upon completion of the Project. The CM shall compile and submit to the Owner daily a summary report consisting of the CM’s daily diary entry and each Contractor’s daily report describing the construction activities of the day along with manpower and equipment usage, including that of the Contractors.
Progress Records. During construction, Contractor shall keep a marked-up and up- to-date set of drawings showing as-built conditions on the site as an accurate record of all deviations between Work as shown and Work as installed. These drawings shall be available to Owner for inspection at any time.
Progress Records. During construction, Contractor shall keep a marked-up and up- to-date set of specifications showing as-is conditions on the site annotated to clearly indicate all substitutions that are incorporated into the Work. Where selection of more than one product is specified, annotation shall show which product was installed. These specifications shall be available to Owner for inspection at any time.
Progress Records. Design Builder will keep detailed records of the progress of the Project during all stages of construction in accordance with the Specifications and this Agreement. Design Builder will also maintain a daily log of all events occurring on the Project Site or connected with the progress of the Project, a log pertaining to all Requests for Information (RFI) submittals and a log for Contingency Use Request (CUR) submittals. Copies of the progress records and logs will be submitted monthly to Owner.
Progress Records. The CM shall keep accurate and detailed written records of School Project progress during all stages of construction. The CM shall maintain a detailed daily diary of all events, which occur at the jobsite or elsewhere, and which affect, or may be expected to affect, School Project progress. The diary shall record weather data, including minimum and maximum temperatures, precipitation type and amount, sky conditions, and wind velocities. The diary shall also record all visitors, number of on-site workers for each contract and include a detailed list of all material deliveries to the site. The diary shall be available to the Owner at all times and shall be turned over to the Owner upon completion of the applicable School Project. The CM shall compile and submit to the Owner daily a summary report consisting of the CM’s daily diary entry and each Contractor’s daily report describing the construction activities of the day along with manpower and equipment usage, including that of the Contractors.
Progress Records. During construction, SLWD shall keep a marked-up and up-to-date set of drawings showing as-built conditions on the site as an accurate record of all deviations between work as shown and work as installed. These drawings shall be available to City for inspection at any time.
Progress Records. During construction, SLWD shall keep a marked-up and up-to-date set of specifications showing as-is conditions on the site annotated to clearly indicate all substitutions that are incorporated into the Work. Where selection of more than one product is specified, annotation shall show which product was installed. These specifications shall be available to City for inspection at any time.
Progress Records. During construction, Construction Manager shall keep a marked-up and up-to-date set of specifications showing as-is conditions on the site annotated to clearly indicate all substitutions that are incorporated into the Work. Where selection of more than one product is specified, annotation shall show which product was installed. These specifications shall be available to Town for inspection at any time.