Punch List Items. Upon Substantial Completion of the Venue Improvements (including the Air Rights Infrastructure), City shall provide notice thereof to Club and BSD. Club Representative, BSD Representative and City Representative shall schedule a time to meet within thirty (30) Business Days thereafter to inspect the Venue and for Club to prepare a “punch-list” of items that are reasonably required to be completed or repaired prior to Final Completion of the Venue Improvements. The Contractor shall complete, or cause to be completed, all reasonable punch-list items relating to the Air Rights Infrastructure within thirty
Punch List Items. Prior to Tenant taking occupancy of any portion of the Premises pursuant to Section 1.6 above, Landlord shall notify Tenant in writing when Landlord considers the Tenant Improvements (as defined in the Work Letter) to be substantially complete and Tenant shall, as soon as possible but not later than three (3) days after notice of substantial completion is received by Tenant from Landlord, conduct a walk-through inspection of the applicable phase of the Premises (or portion thereof) with Landlord. Tenant shall notify Landlord in writing within two (2) days of completing said walk-through inspection of all learns of Tenant Improvements which Tenant reasonably determines must be completed or corrected (“Punch List Items”). Following preparation of the Punch List Items, Tenant shall take occupancy. Landlord shall complete repairs of the Punch List Items within forty-five (45) days of receipt of Tenant’s notice of Punch List Items. If Landlord fails to complete repairs of the Punch List items within said 45 days, neither the Commencement Date nor the Lease Term shall be extended, but Tenant shall be entitled to complete the repairs at Landlord’s cost and may offset the cost of such repairs from any Rent thereafter due and owing to Landlord. Any dispute regarding the completion of the Punch List Items shall be subject to arbitration under the American Arbitration Association rules.
Punch List Items. Notwithstanding anything to the contrary contained herein, at Owner’s sole discretion, Owner may approve the completion of Punch List Items after Final Completion. If Contractor does not promptly complete any remaining Punch List Item, Owner shall have the right to complete such item and Owner’s costs associated with such activities shall be included in the calculation of Total Costs. Notwithstanding anything to the contrary contained herein, however, if the completion of any Punch List Items requires that an LNG Production System or the Facility be shut down or its output curtailed, Owner shall have the option of completing such Punch List Items itself, and Owner’s costs associated with such activities shall be included in the calculation of Total Costs.
Punch List Items. Within 30 days after Substantial Completion of the Project Improvements, Landlord and Tenant shall inspect the Project Improvements and develop a list of items which were not properly completed by Landlord in material accordance with this Lease and the Construction Plans (the "Punch List Items"). Landlord and Tenant shall use their respective good faith reasonable efforts to agree on a mutually convenient date for such inspection and development of the list of the Punch List Items (the "Punch List"). Landlord shall thereafter promptly commence material completion of the Punch List Items within 30 days after the Punch List has been finalized, and shall continue to pursue such completion with commercially reasonable diligence and speed, but no later than 60 days after the Punch List has been finalized (subject to Excused Delays).
Punch List Items. Following the issuance of the final Architect Certificate, MPT, with the cooperation and assistance of the Adeptus Parties, may, within seven (7) Business Days after receipt of the final Architect Certificate, inspect the Property and Improvements and prepare punch lists (each a “Punch List”) setting forth all incomplete, defective or other items of construction not in conformity with the Plans and Specifications and if MPT delivers any such Punch List, the Developer, with the cooperation and assistance of the Adeptus Parties, shall cause all such items to be completed or corrected within ninety (90) days after receipt of such Punch List. If ninety (90) days is an insufficient period of time in which to complete or correct any Punch List item, the Developer may request one or more thirty (30) day extensions of said 90-day period, which extensions MPT shall grant so long as the Developer and the Adeptus Parties are working and continue to work in good faith and diligently pursue the completion and correction thereof. In the event such items are not completed within the ninety (90) day period, or the extended period of time, as applicable, MPT may complete or correct any or all of such items and the Adeptus Parties, jointly and severally (subject to the Guaranty Limitation), shall reimburse MPT for the cost thereof within thirty (30) days after receipt from MPT of written demand for such payment, with interest thereon computed at the Overdue Rate from the date of demand to the date of payment. In the event the Adeptus Parties fail to reimburse MPT for such cost and interest within such thirty (30) day period, such failure shall constitute an Event of Default and MPT shall be entitled to pursue any remedies available against the Adeptus Parties provided herein or at law or in equity.
Punch List Items. The miscellaneous items in the scope of the Project that are not required for the Project to be operational and that remain to be completed by DESIGN/BUILDER after Substantial Completion and before Final Completion.
Punch List Items. The term "Punch List Items" shall mean details of construction, decoration, and mechanical adjustment which in the aggregate, are minor in character and do not materially interfere with the Tenant's use or enjoyment of the Premises. Prior to the Commencement Date, Tenant and Landlord shall inspect the Premises and prepare a mutually agreed upon list of Punch List Items. Punch List Items shall be completed by Landlord within thirty (30) days after Substantial Completion.
Punch List Items. Borrower shall complete all Punch List Items no later than one hundred twenty (120) days following the date on which Substantial Completion occurs (subject to reasonable extensions if Borrower is diligently pursuing the completion of such Punch List Items), or such earlier date as may be required under the School Unit Purchase Agreement.
Punch List Items. Notwithstanding anything to the contrary contained herein, at Owner’s sole discretion, Owner may approve the completion of Punch List Items after Final Completion; provided, however, that if any such Punch List Items remain outstanding at Final Completion, Contractor shall cause the Contractor Guarantee to remain in full force and effect until Contractor’s completion of all of such Punch List Items to Owner’s satisfaction. If Contractor does not promptly complete any remaining Punch List Item, Owner shall have the right to complete such item and Owner’s costs associated with such activities shall be included in the calculation of Total Costs. Notwithstanding anything to the contrary contained herein, however, if the completion of any Punch List Items requires that an LNG Production System or the Facility be shut down or its output curtailed, Owner shall have the option of completing such Punch List Items itself, and Owner’s costs associated with completion of any such Punch List Items (excluding costs associated with shut down or of output curtailment) shall be included in the calculation of Total Costs.
Punch List Items. Lessee shall cause all punch list items respecting each Property to be completed in a good and workmanlike manner within one hundred twenty (120) days of the Completion Date for such Property.